Broomfield Community Center Reconstruction Project

News & Updates.....

Adolfson & Peterson Construction (AP) was awarded the Construction Manager/General Contractor (CM/GC) agreement by Council on January 23, 2018, authorizing the contractor to begin the preconstruction services to include constructability reviews and cost estimating to keep the project within budget.

Davis has completed the schematic design phase and AP is estimating the design drawings and scope narratives. The amendment process to the Site Development Plan (SDP) has started with the SDP Concept Review scheduled for the March 27th Council Meeting. The start date for first phase of construction is anticipated to be mid-August of 2018.

Sign up for email updates!
  1. Schedule & Timeline
  2. Background Info
  3. Concept Plan
  4. Senior Center
  5. Public Input


Schematic Design, Design Development, and Construction Documents are anticipated to be completed by January 2018, April 2018, and November 2018, respectively.  It is anticipated that the delivery method for construction will be conducted in a “Fast Track” method which allows construction documents to be released in phases so that construction can start earlier.  Following Council consideration of a construction agreement, the proposed construction phases would include Phase 1) Demolition/Sitework/Utilities, Phase 2) Foundations/Superstructure, Phase 3) Balance of the Building, and Phase 4) Demolition of Senior Center/Balance of Sitework.  Under this delivery method, it is anticipated that construction would start with Phase 1 (closure of the recreational wing) as early as June 2018, complete the new facility by March 2020.  Remaining balance of the sitework by May 2020.

News & Updates Continued...

Informational Session
A public informational session on the reconstruction of the Broomfield Community Center was held Friday, November 17 at 10 a.m. at the Broomfield Community Center.  Thank you to everyone who attended!

A public meeting was held Wednesday, October 25 at the Broomfield Community Center.  
Click here to view the presentation from the public meeting.
Watch video of the meeting.

Please give us your comments by taking this Survey.

In August 2017, Council adopted Ordinance No. 2053 authorizing the issuance of Sales and Use Tax Revenue Bonds for the purpose of providing funds for the Broomfield Community Center Redevelopment Project (and also the Dillon Road/West 144th Avenue project).

BCC Project Location

On July 11, Council approved a consultant design award to Davis Partnership PC. In addition, Ballard King & Associates LTD, has been awarded an agreement by the City Manager for consulting services to facilitate the public process and development of features and programming to be included in the new facility design. Design investigation, research, and conceptual design is underway, and the public process is expected to start in late August.

The conceptual design involves the demolition of the north half of the facility to allow space on the site for a new facility to be constructed. This would allow the senior services wing of the building to remain open during the construction of a new 2 story Community Center; however, it would require that some programs move to the Paul Derda Recreation Center while others would be discontinued for approximately 18 to 24 months while the new facility is being constructed.